COVER STORY                                             elements within the highly congested area with vary narrow
          REPORT                                               •   road to the project site.

                                                                   Use of special lifting tools to increase the execution such
                                                                   as remote ground release shackles, site developed multiple
                                                                   beams lifting tools, high speed bolting tools to achieve
                                                                   specified torque values.
                                                               •   Use of noise reduction bolting torque machines to reduce
                                                                   the noise to 40 db without compromising on the bolting speed.
                                                               •   Use of surveying tools like total stations and lasers for
                                                                   measurement accuracy and importantly the verticality of the
                                                                   structure to achieve the stability.

                                                               Challenges faced during the erection
                                                               •   Tower Cranes inside the building - The constrained project
                                                                   space area and adjacent residential area challenged the
           The building has car parking facility up to 6th stilt level and above 12   aerial area for movement of the Tower Crane, which forced
           floors as Office Space. Total Height of the Structure above ground   to install both the Tower Cranes inside the building.
           level is 71.962 meters with floor plate of 6,450 square meters.   •   Use of Noise reduction tools and  tackles -  Control  on
           The project is designed as Composite Steel Structure with Grid of   noise pollution called for use of Low Noise Bolt Tightening
           11 m x 9 m, concrete infilled box columns with optimized size i.e.   equipment’s deployment, without compromising the speed
           up to Stilt Parking Area 1100 mm x 950 mm and above office floors   of construction activity.
           columns of size 600 mm x 600 mm to maximise the floor carpet   •   Logistics – Transportation of the steel structure elements within
           area.                                                   the city area and live IT campus.
           The floor to floor height for parking area is 3300 mm and office   •   Dimensional accuracy of the Structure – the proper planned
           area is 4150 mm.  Fire proof paint used for columns is Vermiculite   structure erection works with regular level dimensional checks
           Coating and Intumescent Paint.                          to achieve the specified size and verticality of the structure.
           Over 2.6 lacs safe man hours achieved with deployment of an   The entire building above stilt levels i.e. office floors are having
           average 60-65 workmen crews daily.                      façade with dimensional accuracy to be maintained. The
                                                                   building stability calls for stringent verticality measurements,
           Description about the structural elements               with help of the Total Station and site developed tools used to
           All the Columns are Box Columns with concrete infilled and Beams   achieve the verticality within 6 mm.
           are I-Sections. Deck Sheeting is TR 60 with composite action.
                                                               Safety Initiatives
           Uniqueness about the structure                      •   Safety of Crew during Construction works – Induction of
           The Composite Steel Structure is developed for vertical spaces.   new crews with health checkups for the vertigo test. Daily Tool
           The box columns with concrete infilled are highly optimized   Box meeting with construction crew and orientation of daily
           and  sectional  element  thickness,  built-up  “I”  Section  Columns   activities prior to start of the work.
           connecting with RCC central core and peripheral four corner RCC   •   Stringent protocols follow-up for sanitation and hygiene of the
           shear wall staircases, cantilever of 2400 mm on periphery with   labour colony.
           planter boxes.                                      •   TPI’s of all the lifting equipment and tools and tackles.
           All the elements of the building are double side welded as per   •   Used special equipment for safe erection with speed such
           the AWS standards with high end electrodes to have the highest   as Tower Cranes, Deck Riders over the slabs at every level to
           precision, consistency and efficiency during welding.   access the height members in above floors, use of the beam
           Grade of Steel used is Fe450                            roller crawlers for anchoring the safety harness.
                                                               •   Heat stress management – Project passed through the severe
           Techniques used for erecting the structure              heat weather and summer climate during which daily health
           •   Total Project Management – Alignment of the Engineering,   checkup of all the workmen.
              Production and Supply chain with site construction activity.  •   Covid-19 Safety of working crew – Regular sanitization of
           •   Just in Time Philosophy – the production of the structural   materials received at site and training and orientation to
              members were as per the construction plan and shipment of   the crew including daily health monitoring. Labour colony
              the same with continual monitoring.                  sanitization and regular health checkups helped in retaining
           •   QA/QC techniques – with meticulous and methodological   the entire workforce during entire lockdown period of 45 days
              approach, quality checks were implemented at all the stages   and started the construction as soon as the clearance was
              right from Raw Material to Finished Goods at plant with the   given for commencement.
              client’s QA/QC team involvement at every level for smooth
              execution of the project.                        For more details visit:
           •   Meticulous Logistics plan – Transportation of the steel structure   www.kirbyinternational.com